September 13, the 23rd Typhoon ' Bai Jia ' in Zhanjiang landed, the center of the largest wind 10 level.
September 16 16:00, is located in the "Mountain bamboo," the hardest hit the Guangdong Red Sea Bay Power Generation Co., Ltd. called an emergency call, the maintenance of electrical production of a 720 KVA/500,000 KV main transformer in the ' Mangosteen ' typhoon in the occurrence of damaged components and other disasters, demand prompt dispatch of people to help repair.
Disaster is the order, time is life, the disaster quickly reflects the credibility of enterprise Services!
Wen Hung electric Secretary, chairman of the board, General manager, Deputy Secretary of the party committee Liu Shujuan and other company leaders attaches great importance to the immediate deployment of repair tasks, request technical service personnel rushed to the ' Mountain bamboo ' disaster area, to ensure that Red Sea Bay Power Generation Co., Ltd. to resume operations as soon as possible. The first time to hold a special meeting, set up by the deputy general manager Zhou Eidong as the leader, by the process, design, marketing services and other departments party members of the backbone of the rescue commandos, the deployment of repair tasks, and request technical service personnel immediately rushed to ' mountain bamboo ' typhoon disaster site, to ensure that the Red Sea Bay Power Co., Ltd. main transformer resume operation
. As of 21:00 September 18, the mission of the emergency commando members of the company's general technologist Zhao Jing Month, marketing company business Director Wangguodong, design director of the designer Cesl education and marketing services staff Shulin, Zhaozongjie and other party members, technical backbone, overcome the traffic and communication difficulties, in the case of airport aircraft outage,
By high-speed rail and car overnight rushed to the ' Mountain bamboo ' disaster area. That night 22:20, under the leadership of Zhou Eidong, the commandos did not take the road fatigue, rushed to the Red Sea Bay Power Generation Co., Ltd. damaged main transformer site, check the transformer failure, understand the damage of the transformer, and with the power plant technicians to develop maintenance plan.
Everyone stayed up all night, held overnight failure analysis will be September 19 3:00, put forward the preliminary treatment advice arrangement next repair work. September 19 10:00, all the commandos to the scene of the fault transformer key parts of the re-examination and analysis. As of now, the maintenance of the damaged transformers for electrical repair is ready. Red Sea Bay Power Generation Co., Ltd. 720 KVA/500,000 KV main transformer damaged parts procurement and transportation work has been arranged in the shortest time.
Change Electric said, will lift the power of the whole company, as soon as possible to restore power to the disaster area. During the rescue process, Wen hung several times to call the commandos to understand the technical support and material security of the disaster-stricken areas of the implementation of the situation, and to the rescue team to express their condolences, the company requested the relevant contingency plans to ensure that repair work foolproof.
Liu Shujuan and other company leaders also call in the first time, told the frontline staff in doing their own security protection work, quality and quantity to complete a good repair task, to make positive contributions to the disaster area rescue It is reported that the change of electrical has called the Red Sea Bay Power Generation Co., Ltd., will strive to provide services for the disaster area, to recover as soon as possible the main transformer operation.