August 23, Luzhou Gulin ushered in a group of 58.6 meters long, weighing nearly 13 tons of blades, after a week, these huge blades from Henan Luoyang through road transport to Gulin.
What is the blade so long, so heavy? It turns out that this is the first wind turbine blades of the Gulin County-Guang nuclear power plant, which arrived in Gulin from Luoyang, Henan province.
It is reported that this is the first wind power plant in Luzhou. The reporter learned from the Gulin County power supply Company, the medium-and-broad nuclear Gulin de Yiu wind power generation, is expected to be equivalent to nearly 4 months of total electricity consumption.
It is worth mentioning that after the operation of the Wind power generation project, it can further improve the voltage, improve the power quality of villages and towns, lighten the power generation cost of the county, reduce the development of thermal power generation and hydropower projects, and play an important role in energy conservation and environmental protection. The project will also become a major tourist attraction.
How to transport nearly 60 meters long blades? With the rapid economic development, before the traditional energy began to be phased out, the new energy came out, wind power is one of them.
However, we may be very puzzled, 58.6 meters long, weighing nearly 13 tons, can not be assembled separately, so the bulky blade is how to transport the mountain?
The reporter consulted the director of the Gulin project, and he gave the answer.
Originally, the Blades of the mountain is dedicated to carry the loading of the vehicle, the car mounted a 360-degree rotatable device, using the blade front-end flange piece and car body of the rotatable device connection, in the face of large curvature or other obstacles, make the blade follow the body can rotate the device transformation angle.
For example, in the transport vehicle on the left side of the car appeared a tree, or a raised rock, then the transport of the Blades of the truck can be like a robot to "accept instructions," to achieve the right to move to the right, the tail pendulum, you can pass obstacles.
Not only technologically advanced, transport officials said, because the Gulin section of the mountain Road rugged, more corners, in the actual transport, has been on the road ' transformation ' to the overhead line, turning radius to measure, to ensure the smooth arrival of the blades. The transport related person said that the project will be a total of 72 blades of transport. The first batch of transport 6 to Gulin County, is expected to be in early September to the construction site loading. Project location altitude between 1570m to 1820m, wind speed reached 5.6m/s, suitable for wind power generation.
There are 24 sets of wind turbine generators in the field, and the annual net electricity output is expected to reach 90 million degrees. Single leaf length 58.6 meters! The first wind power station in Luzhou, Sichuan province is built