Liaoning Electric Power accelerated the pace of construction of Fushun Power Grid. During the 13th Five-Year Plan period, it planned to invest 6.31 billion yuan to make a positive contribution to the revitalization of Fushun.
On February 22nd, State Grid Liaoning Electric Power Co., Ltd. and Fushun Municipal People's Government signed the “Framework Agreement for Development Cooperation of Fushun Municipal People's Government of State Grid Liaoning Electric Power Co., Ltd.” This is the complementarity between the government and the grid enterprises to achieve a win-win situation. Advantageous measures are an important means of forming synergies and accelerating development.
At present, Fushun has a total of 110 public substations of 66 kV and above. Among them, one 500 kV substation, 14 220 kV substations, 95 66 kV substations. 66 kV and above substation capacity 10.382 million kV Ann, line 3587.1 km; 10 kV public network with 6696 units, capacity of 1.508 million kVA, 493 lines, total length 6825.9 km.
During the 'Twelfth Five-Year Plan' period, four 220 kV substations were put into operation in Fushun, with a new substation capacity of 1.83 million kVA and a new line of 109.6 km. This is an increase of 62.2% and 14.4% respectively from the end of the '11th Five-Year Plan. New (expanded) 18-seat 66 kV substation, with a new 66 kV substation capacity of 1.325 million kVA, and a new 66 kV line 397.2 km, an increase of 54.7% from the end of the '11th Five-Year Plan, 26.9 %; New 10 kV line length is 1897.3 km, up 18.2% year-on-year. In addition, the construction of rural power network has completed an investment of 960 million yuan. State Grid Liaoning Power has passed a series of construction projects, which has ensured the largest electricity consumption in Fushun. The power supply requirement of 2.047 million kilowatts of load provided strong power guarantee for economic development; the power supply capacity of the rural power grid, the reliability of power supply and the level of equipment have been significantly improved, and the special renovation project of central villages and villages has effectively improved the rural areas. Power quality, eliminating the long-standing problem of low voltage and insufficient power supply.
During the '13th Five-Year Plan' period, the Fushun Municipal Party Committee and Municipal Government will give full play to the active role of the power grid construction and power facilities protection leading group, conscientiously implement the main responsibility, and do a good job in coordination and promotion of power grid construction; around Fushun City's 'One Extreme Five Industry' The development of large energy industry requires solving problems together, accelerating the development of power grids, giving more power support to the energy sectors of emerging industries, and contributing to Liaoning's revitalization and local development. State Grid Liaoning Electric Power always takes 'people's electricity industry as the people' as its purpose, Actively integrate into the overall situation of local government work, earnestly implement the terms of the agreement, continue to increase investment in Fushun Power Grid, go all out to accelerate the construction of a strong smart grid, serve economic and social development, serve power customers and power generation enterprises, and actively connect with governments at all levels. To carry out power grid planning and construction ahead of time, optimize the service flow of electricity, meet the needs of local economic development, park construction and customer industry expansion, and accelerate the transformation and upgrading of Fushun City, and make positive contributions to the new round of revitalization and development.
During the '13th Five-Year Plan period, Fushun Power Grid planned investment of 6.31 billion yuan, a year-on-year increase of 47.1%, focusing on the weak distribution network grid, long power supply line radius, local area power supply 'card neck' and clean energy consumption To meet the needs of industrial parks and county economic development, plan to build a 500 kV Qingyuan pumped storage power station to Fushun transformer line (191.2 km) to meet the needs of the Qingyuan 1.8 million kilowatt pumped storage power station to deliver electricity. Liaoning Power Grid clean energy consumption problem; plan to build four 220 kV substations, expand (renovate) two 220 kV substations, build new 220 kV lines 13.9 km; plan new (expanded) and rebuild 66 kV substation 48 Block, the new line is 773.3 kilometers, and the newly added substation capacity is 3.277 million kVA, meeting the needs of the park (jing) area and major projects.