National Energy Administration: First Demonstration Project of Solar Thermal Power Deferred until 2020

On May 22nd, the National Energy Administration issued the Notice on Promoting the Construction of Solar Thermal Power Demonstration Projects to implement the requirements for demonstration project construction and accelerate the construction of demonstration projects.

In September 2016, China launched the first batch of 20 solar thermal power generation demonstration projects. The main contents of the notification are as follows:

Establish electricity price fallback mechanism. According to the actual conditions of the demonstration project, the construction period of the first batch of demonstration projects can be relaxed to December 31, 2020. At the same time, the mechanism for electricity price fallback for overdue investment projects will be established. The specific price level will be determined by the price division of the National Development and Reform Commission. Clear text.

Establish a construction content adjustment mechanism. To promote the development of solar thermal power generation industry, without affecting the fairness and fairness of the industry, the demonstration project owner can make appropriate adjustments to the relevant demonstration construction content. The relevant adjustments should meet the following requirements:

(1) The change of shareholding structure requires the maintenance of an absolute controlling party;

(2) The scope of construction site change is within the same county area;

(3) The adjustment of the heat storage medium and technical parameters must ensure that the system performance is optimized;

(4) Adjusted technology integrators can be adjusted if the relevant companies agree on the agreement;

(5) Other model contents may not be adjusted in principle.

The adjustment of construction content shall be reported to the provincial energy authority for technical support agencies to organize the research and validation and implementation of the relevant procedures, and shall be completed by the end of June; the provincial energy authority shall promptly submit the demonstration content adjustment report to the National Energy Administration.

Establish a project exit mechanism. According to the “Circular of the General Affairs Department of the National Energy Administration on the Construction of CSP Demonstration Projects” (hereinafter referred to as the notification), the provincial-level energy authorities should cooperate with the demonstration projects listed in the notification. Well related aftermath work;

For the demonstration projects listed in the notification that have not submitted the construction commitments in the past due time, the project demonstration qualifications will be cancelled and the model policies will no longer be enjoyed;

The demonstration project investment enterprises that are committed to continue construction as listed in the notification shall follow the planned start time and planned production time specified in the notification, and implement the safety production responsibility and project quality requirements at the same time to ensure that the demonstration project is completed and put into production.

For those project investment enterprises that have not started or put into operation according to the specified time limit, they will be notified according to the circumstances or restricted to participate in the construction of follow-up solar thermal power generation demonstration projects.

The following is the full text of the "Notice"

Qinghai Province, Gansu Province, Hebei Province, Inner Mongolia Autonomous Region, Xinjiang Autonomous Region Development and Reform Commission (Energy Bureau), Price Bureau, State Grid Corporation of China, Investment Companies for Solar Thermal Power Demonstration Projects:

In September 2016, the SIPO issued the “Circular on Building a Solar Thermal Power Generation Demonstration Project” (Guoneng Xinneng '2016'223, hereinafter referred to as “Notice”), and started construction of the first batch of 20 solar thermal power generation demonstration projects. We will implement relevant requirements for the construction of demonstration projects, accelerate the construction of demonstration projects, and ensure the effectiveness of the implementation of the demonstration projects. The National Development and Reform Commission of the People's Republic of China, the Price Division and the Basic Division, will now notify the relevant issues as follows.

First, unify thinking and attach great importance to demonstration project construction

The first batch of demonstration projects of solar thermal power generation is the first large-scale demonstration project of solar thermal power generation in China. It is an important measure to promote the progress of solar thermal power generation technology and industrial development. The smooth construction and operation of the project is of great significance for demonstration-led industrial development. The competent energy authorities and investment enterprises of demonstration projects, as responsible subjects for the construction of demonstration projects, must pay great attention to them, highlight their goal orientation, earnestly perform their main responsibilities, and do a good job in the various tasks of the demonstration projects to ensure that projects with construction conditions are completed and put into production as required. Give full play to the exemplary role of lead.

Second, take multiple measures to focus on building a project promotion mechanism

(I) Establishing Electricity Pricing Slope Reduction Mechanism

The "National Development and Reform Commission Circular on the On-grid Price Policy of Benchmarking Solar Thermal Power Generation" (development and reform price '2016' 1881) made it clear that the first batch of demonstration projects completed and put into production before December 31, 2018 will be executed at 1.15 yuan per kilowatt-hour (including (tax) benchmarking on-grid price. According to the actual situation of the demonstration project, the construction period of the first batch of demonstration projects can be relaxed to December 31, 2020. At the same time, the electricity pricing mechanism for overdue investment projects will be established. The specific price level will be determined by the price department of the National Development and Reform Commission. Clear text.

(B) the establishment of construction content adjustment mechanism

In order to promote the development of solar thermal power generation industry, without affecting the fairness and fairness of the industry, the demonstration project owner may make appropriate adjustments to the relevant demonstration construction content. The relevant adjustments shall meet the following requirements: (1) The absolute controlling party shall be maintained for changes in the ownership structure. (2) The scope of construction site change is within the scope of the same county; (3) The optimization of system performance must be ensured for the adjustment of heat storage medium and technical parameters; (4) Adjustable technology integrators through consultation among related companies; ( 5) Other model contents may not be adjusted in principle. The adjustment of construction contents shall be reported to the provincial energy authority for technical support agencies to organize the research and validation and implementation of the relevant procedures, which shall be completed by the end of June; the provincial energy authority shall provide demonstration content. The situation of adjustment and approval shall be reported to the Bureau in time.

(III) Establishment of Project Exit Mechanism

According to the “Circular of the General Affairs Department of the National Energy Administration on the Construction of the CSP Demonstration Project” (hereinafter referred to as the notification), for the demonstration projects listed in the notification to be withdrawn actively, the provincial energy authority in charge shall cooperate with the relevant aftercare work; For the demonstration projects listed in the notification that have not submitted the construction commitments that are not submitted within the time limit, the project demonstration qualifications will be cancelled and the demonstration policies will no longer be enjoyed. The demonstration project investment enterprises listed in the notifications that are committed to continue construction shall follow the schedule and schedule clearly stated in the notification. The production time, the implementation of safety production responsibilities and project quality requirements, ensure that the demonstration project is completed and put into production. For project investment companies that do not start or put into operation according to a specified time limit, they will be notified according to the circumstances or restricted to participate in the follow-up of solar thermal power generation demonstration projects. .

Third, to strengthen collaboration, multi-joint action to form a joint effort

(1) The Bureau will work closely with relevant parties, strictly follow the “Notice” provisions and related requirements, supervise and guide the implementation of demonstration projects, establish and improve and strengthen the implementation of the three working mechanisms of “retreat, adjust, and withdraw” and the system of untrustworthy punishment. , To ensure that the first batch of demonstration projects play a leading role in the industry.

(2) The provincial energy authorities of each demonstration project site shall promptly carry out the project construction promotion work, and at the same time strengthen the service guarantee and organization coordination. In particular, they must communicate well with local governments and power grid companies to ensure the progress and quality benefits of the project construction. .

(3) The State Grid Corporation of China shall, in accordance with the requirements of the “Notice” and in conjunction with the definite plan construction progress of each demonstration project, timely carry out the construction of the supporting grid transmission project, and study in advance the grid-connected operation plan after the demonstration project is put into operation to ensure that all the demonstration projects generate electricity. The amount of consumption.

National Energy Board

May 18, 2018