Construction of Zhejiang Petrochemical ethylene project to promote steady progress


In recent days, Zhejiang Petrochemical and Ethylene Project Department, the ten construction company of Refinery and Chemical Engineering, took advantage of the current favorable opportunities of less rainfall, less wind and temperature rise in Zhoushan, and quickly set up the construction climax of professional pipe and equipment, steel structure and anti-corrosion and heat preservation. , The entire project construction site showed more flowering, big and fast, good and efficient good situation.

It is understood that 1.4 million tons / year of ethylene project in Zhejiang Petrochemical to achieve high standards in the October 30 to pay, effective construction period of less than 9 months time. Facing unusually tight construction period, the construction of ethylene project in Zhejiang Petrochemical Division to 'change the concept, brave to assume responsibility, a benefit' for the project operating ideas, 'innovation in management' work hard on the 'efficiency to enhance' homework to do. Project Department has always been 'dry ethylene, the first fight' for the Goals, adhere to the planning precedence, brainstorming, through the retreat, thematic meetings, formulate specific programs and measures to guide the owners, guide the subcontracting, leading the construction; fully to the owners think, Urgent anxious owners, so as to establish a good Service image; at the same time pay close attention to on-site safety, quality and civilized construction management to ensure the steady progress of the project.

Aimed at the key line of underground pipe network construction of ethylene plant, the project department broke through the routine and overcame the unfavorable factors such as the lag of pipe drawing, lack of material arrival and complicated geological conditions. Through a series of practical measures to ensure the project construction is promoted efficiently, Is the initiative and design communication, according to the site construction conditions give priority to the map; the second is the joint owners, supervisors held a special planning meeting to change the way to test the ground pressure to replace kerosene hydraulic pressure test; third is to change the subcontracting mode to increase the construction team , The project will be quantified as zero, a number of teams to work together; Fourth, put into full automatic welding equipment and large crane, increase precast depth.At present, the ethylene pipeline construction of underground pipe network is nearing completion.

As of January 21, the project to build ethylene in Zhejiang Petrochemical Company has completed 21,182-inch diameter pipe installation, 3090 tons of steel structure installed and two largest equipment of ethylene plant, No. 1, The No. 2 propylene tower successfully completed modular hoisting. The safety, quality and progress of the entire project are under control.

2016 GoodChinaBrand | ICP: 12011751 | China Exports