January 6, learned from the construction site of Tianjin Nanjiang Storage and Transportation Project Recently, with the completion of the last tank storage of T201, the storage and transportation project in southern Xinjiang of Tianjin was smoothly Achieve 20 storage tanks to complete the construction control node, laying a solid foundation for completion of Tianjin Southern Xinjiang storage and transportation project on schedule.
There are 20 storage tanks in Tianjin South Xinjiang Storage and Transportation Project, including 6 30000m³ storage tanks, 6 20000m³ storage tanks and 8 8750m³ storage tanks, with a total of 56677 pieces of quality inspection during construction welding. Construction preparation time is short, the tank construction program argued for a long time and other difficulties, the first tank construction began on July 8, 2017. Faced with large quantities of storage tanks, high altitude, confined space operations, storage tank deformation prevention measures Implementation difficulties and other unfavorable factors, the project department meticulously organized, scientific arrangements, surprise focus, peak at the same time seven tank construction, more than 230 operators, to ensure that each construction tank control node.Especially in the project construction period, coincides with the In summer, not only should operators not only be exposed to the heat and heat of welding, but also to the test of heat radiation during welding, they should also overcome the unfavorable factors of construction in the tank and actively take effective measures to ensure the progress of construction. In combination with the actual construction, Labor competition, improve work efficiency, security quality, catch up, and promote construction.
The project department always adheres to the management concept of "safety first and quality first" to realize the safety education right of operators covering 296,000 workers without artificial accidents. Strict implementation of welding process, perfect deformation prevention measures, overall tank construction The pass rate of 98.33%, higher than the qualified rate of the contract, but also to ensure the quality of tank construction, owners and other departments to be praised.