The second crane of Nanjing Engineering Yangzi Petrochemical Power Plant desulphurization project was successfully put into place


On the morning of November 29, the second large-scale hoisting crane for the steel structure of the desulphurization project of the Yangzi Petrochemical Power Plant in Jiangbei Branch of Nanjing Engineering Co., Ltd. was smoothly hoisted. As the 53.8-57.7-meter-long framework was steadily in place, the progress of the project achieved a new breakthrough. Lifting process takes 1.5 hours, due to the steel structure of the cross steel columns, six column foot butt, and the site is small, the size of the structure, the site is high, the installation and lifting work more difficult than conventional large hoisting significantly increased through the project department Organized planning, close implementation, the overall process smooth, docking accuracy control is very good.

Lifting

In place

2016 GoodChinaBrand | ICP: 12011751 | China Exports