November 23, from the ongoing construction of Hengyi Brunei pmb petrochemical project site was informed by the four petrochemical companies and other employees involved in the management of Hengyi Brunei pmb petrochemical project desalination unit sea pump room construction progress to the foundation excavation last As the deepest foundation pit, slope support and settlement observation as the focus of quality control, with this last layer, the construction of the most difficult and most crucial layer of excavation nearing completion, marking the earth from the open Digging turned to civil construction.Photo, seawater desalination unit seawater pump room construction is entering the last layer of excavation.
The picture shows the seawater desalination plant seawater pump room construction is entering the last layer of excavation.