Under the careful organization and implementation of ten construction projects department, after large-scale hoisting, the equipment installation workers worked closely for 6 months to build 15/48 tons / year EO / EG plant of CNOOC Huizhou Refining & Chemical Co., Ltd., Weight 5600 tons of large-scale overrun equipment, to November 13 all hoisting completed.
The 20 units exceed the limit, with 9 units weighing more than 200 tons, of which the heaviest equipment is R-101 EO reactor of 1,100 tons.It attaches great importance to the hoisting of large-scale equipment, conscientiously drafting lifting plans, scientifically organizing each large-scale hoisting According to the equipment arrival plan date, they complete the construction of the crane group station car and equipment foundation ahead of schedule. The use of three large cranes of 2,000 tons, 750 tons and 400 tons is planned and arranged in a safe manner so that it can complete large-scale equipment hoisting Work at the same time, as far as possible within the scope of large crane hoist within the radius of the other small and medium sized equipment, steel framework of the lifting module installed to improve the utilization of large cranes, so as to reduce costs and improve efficiency.Especially lifting the heaviest in May R -101 reactor, the whole hoisting crane and crane work closely with the three days to complete the 400-ton crane group car, 15 days to complete the 2000-ton crane group car, making this the most super-Thousand tons of reactors in May Safe and successful lifting on the 17th successful.
In this way, after all the personnel involved in the construction of the brave and hard work, and ultimately safe, high quality and efficient completion of all overrun lifting equipment installation tasks in order to promote the project on March 30, 2018 completed in the construction of a solid foundation.