Ten reconstruction unit supporting system installed three main storage tank finished


Maoming Petrochemical 1.5 million tons / year continuous reforming equipment supporting the reforming tank area three 5000 cubic meters tank, on October 31 the main installation is complete, one of the tanks are being filled with water for pressure test; since the end of August Since the installation of a tank floor, ten project company organized carefully organized, safe, strict quality management, storage tank operators do hard work, struggling to build the main body to install the tank.

Each of the three cans has a diameter of 21 meters, a height of 18 meters and a weight of 146 tons, which are made by welding 45 bottom plates, 72 wall plates and 24 roof plates.Because the three cans are located in the old tank area, Due to the cross-cutting effect of production and construction depth, it is relatively late to meet the basic production and tank installation conditions. The installation of the three tanks must be completed and put into use by the end of this year.

Ten Construction Project Department attaches great importance to this, as early as late August held at the tank area construction project symposium stressed: 'The end of October must complete the main tank installation, the end of December must be fully installed to complete the handover workshop.' Facing the tight schedule , The tank farm moving fireworks strict, Maoming more rainy days and many other negative factors, the three tank construction from the beginning based on a 'grab' word, hard work more than ten hours a day, especially in each tank installation In order to ensure the completion on schedule, a new welding operation group was added on the basis of the original three staffs of the welding and welding operation team, A number of measures: cutting from the steel plate, to the coil pressing, and then to the lifting group, the welding of each tank seam welding implementation of water operations; in order to minimize the impact of rainy weather, good weather as far as possible arrangements for tank operations, rainy days Into the tube welding; to speed up the work of each strip welding, but also to each strip of 89-meter-long seam evenly distributed to each welder, 89 welders in the wall welding started a quality, speed , The first 'than learning ultra-rush help' labor competition, overtime every day to 20:00.

In this way after 25 riveting workers, welding and other staff tenaciously hard work, and finally completed according to the plan of three 5000 cubic meters of storage tank installation of the main task.

2016 GoodChinaBrand | ICP: 12011751 | China Exports