In Maoming Petrochemical 1.5 million tons / year continuous reorganization equipment insulation, ten construction project carefully organized and coordinated, all the anti-corrosion insulation construction workers struggling to scrap, to October 26 device static equipment to complete the insulation, a block of bright silver tower And the silver reflector of the condenser, the continuous re-device 'wear' a new form of beautiful landscape.
Continuous reorganization device and its project with a total of 171 sets of insulation equipment, a total of 1640 cubic meters of insulation, especially 11 high tower equipment, the height of 45 meters to 84 meters, for these towers of the insulation construction, ten Build a scientific organization of the company, the implementation of the ground modular construction strategy, all the towers of the insulation construction, all in the tower before the lifting of the state under the insulation to complete, so that all the tower insulation work all the ground to 6 meters height, thus saving The height of the scaffolding erection and vertical transport of materials, thousands of cubic meters of insulation materials, vertical transport, shelves and insulation staff climb up and down all day long time and labor consumption, but also to ensure the quality of insulation construction and safety of workers, and finally Large tower implementation of modular lifting, saving time and effort to greatly improve work efficiency, but also establish a good image of the construction.
Ten construction of the insulation attaches great importance to the insulation before the start of the construction, careful planning to deploy, carefully prepared insulation construction program, the selection of high quality and hard work of the professional team, and fully build the construction technology, safety, quality work to ensure that Various insulation construction according to the standard.
Maoming weather often under heavy rain and rainy rain, fear of rain insulation construction is very unfavorable, which ten built in the insulation before the construction of the cloth with the color of the cloth to cover all the equipment, or in the equipment above the shelter shelves, so that equipment Insulation is not affected by cloudy rain, to further ensure the quality of insulation and duration.
In this way, under the strong organization and coordination of the ten companies, the equipment insulation construction progressed smoothly and completed on schedule, which established an important condition for the further construction of the continuous reorganization device.